Sample project · no sign-up required
beechwood apartments
A real VE log from a real plan set. Every line below is sourced, reviewable, and honest about what it can’t cite. This is the raw output before any review; approvals and declines happen after you sign up.
Rationale
Premium→mid tier sub. Standard architectural aluminum canopy systems with identical 8" J fascia and Kynar finish. 25-35% savings on canopy scope.
- Source
- Sheet A.201 · Schedule 10.70K
- Spec
- 10 70 00
- Downstream
- —
- Division
- 10 70 00
Rationale
Premium→mid tier sub. Standard architectural aluminum walkway canopy systems with identical 8" J fascia and Kynar finish. 25-35% savings on canopy scope.
- Source
- Sheet A.201 · Schedule 10.70L
- Spec
- 10 70 00
- Downstream
- —
- Division
- 10 70 00
Rationale
Premium→value tier sub, 50-60% savings. Standard 12" concealed bracket at 32" O.C. spacing. Visual equivalence in concealed application.
- Source
- Sheet A.450 · Schedule C-12
- Spec
- 06 41 00
- Downstream
- —
- Division
- 06 41 00
Rationale
Premium→mid tier sub, 35-40% savings. Standard steel counter support bracket maintains structural capacity.
- Source
- Sheet A.450
- Spec
- 06 41 00
- Downstream
- —
- Division
- 06 41 00
This is the output shape VEbase produces on every project. Upload your own plan set and see it on your drawings.
Upload a plan set